Presales, lender conditions and debt cover when rates rise
A construction lender tests a project on presales, debt cover and the buyers behind the contracts. A worked example shows how a 25 basis point rise reaches each test, and what the RBA says lenders are doing now.
A construction lender is repaid from settlements. So before it advances a dollar, it wants evidence that buyers exist, that they will settle and that the sale proceeds cover the debt. The evidence takes the form of presales, a debt cover test and a set of covenants. A rise in the cash rate puts pressure on all three.
This article sets out how those tests can work, runs the arithmetic on a worked example, and records what the RBA says lenders are doing now.
What the RBA says lenders are doing
The RBA's October 2026 Financial Stability Review describes lending terms for commercial property, including residential development. It says competition among lenders had led to some easing in terms over recent years. Some lenders had loosened loan covenants or lowered presale requirements for residential developments, although other terms generally remained unchanged. It also says standards appear to have been largely unchanged more recently. It adds that this easing had been somewhat offset by lenders being more discerning on project fundamentals, including location, and by dealing with established builders and developers.
For private credit, the review says recent liaison suggests some tightening of financial conditions and an increased sensitivity to project risk. That may affect access to funding for some borrowers who usually rely on these lenders, including some residential property developers. The review adds that information on non-bank and private credit lending is limited.
So the picture is mixed. Terms have not tightened across the board, and lenders are choosier about which projects they back. The next rate decision is a reason to confirm where your own lender stands before a condition is tested.
How the tests work
The following figures are illustrative. They demonstrate the method and will vary by site, council and timing.
Take eight townhouses at $1,200,000 each, with gross realisation of $9,600,000, and a construction facility limit of $6,000,000. Assume these lender conditions, which are illustrative only; a real term sheet will set its own:
- Debt cover: net presale proceeds must be at least 1.10 times the facility limit.
- Net proceeds are the contract price less 2.5% selling costs, which is $1,170,000 a townhouse.
- Presales must be exchanged before the first drawdown.
The facility needs net presale proceeds of $6,000,000 × 1.10 = $6,600,000. Five presales give $1,170,000 × 5 = $5,850,000, which is 0.975 times the limit. That fails. Six presales give $7,020,000, which is 1.17 times, and passes. So the project needs six of its eight townhouses sold before funding starts.
What a rise changes
A rate rise does not alter the arithmetic above. It acts on the buyers who sit behind the contracts.
APRA expects banks and other authorised deposit-taking institutions to assess a borrower at a rate at least 3 percentage points above the loan rate. The expectation dates from October 2021 and does not apply to non-bank lenders. In the RBA's lending rate table F6, the average new owner-occupier variable rate was 6.2% in July 2026. If a lender passes on the full September rise, it becomes 6.45%, and the assessment rate becomes 9.45%.
Take a buyer of a $1,200,000 townhouse who needs an 80% loan, which is $960,000. Suppose the household can carry a repayment of $7,900 a month. On a 30-year loan, the maximum loan at a 9.20% assessment rate is $964,527. At 9.45% it is $943,612. The buyer who cleared the test with $4,527 to spare now falls $16,388 short.
Now run that through the debt cover test. Suppose two of the six presale buyers sit in that position and cannot find the shortfall. Net presale proceeds fall from $7,020,000 to $1,170,000 × 4 = $4,680,000. The debt cover is $4,680,000 ÷ $6,000,000 = 0.78 times. That is below the 1.10 minimum, and below 1.0 the presales no longer cover the debt at all. What the lender may do then depends on the facility documents. The developer's options are to resell the two townhouses, find equity or renegotiate.
The effect arrives at settlement. A presale signed when the buyer qualified is tested again if the buyer's lender re-assesses them, and that assessment uses whatever rate applies then.
The interest side
Interest is the other pressure on the facility. It rises with the rate, and on a capitalising facility it uses headroom in the limit. On an average drawn balance of $3,300,000 over 18 months, each 25 points adds $3,300,000 × 0.0025 × 1.5 = $12,375. That is small against $6,000,000. It matters when the facility is already tight against loan-to-cost or loan-to-value limits, because where a lender measures its tests at the limit, every dollar of extra interest takes up space.
The cash rate target stands at 4.60% from 30 September, per the RBA's decision table. Run the interest line and the presale test together. A project can pass each in isolation and fail when the two move at once.
What to check
- Your covenants, in writing. List every test in the term sheet: presale minimum, debt cover, loan-to-cost, loan-to-value, and the dates by which each is measured.
- Your buyers. For each presale, ask what loan the buyer needs and when their approval was issued. Compare the loan with their capacity at the lender's rate plus 3 points, if the buyer's lender is a bank.
- Your headroom. Work out how many presales can fail and still leave the debt cover above the minimum. In the example, six presales give 1.17 times against a 1.10 minimum. Losing one leaves five, at 0.975 times, so the project can absorb no failures.
- Your private lender. If your facility is from a non-bank or private credit lender, ask how it handles project risk now. The RBA says recent liaison suggests private credit funds have become more sensitive to project risk.
- Your plan B. Decide before the settlement date what you will do if a buyer cannot settle: resell, extend, or inject equity. The cost of each should be in the feasibility.
The earlier piece on presale coverage and construction finance gives the wider background.
This is general information and not financial advice.
Published by the SiteLogic Editorial desk. Every fact traces to a primary source. See our standards and corrections register.
Fact-checked: 3 October 2026 · Review by: 3 January 2027
Sources: rba.gov.au · apra.gov.au · rba.gov.au · rba.gov.au
Was this useful? Try the tool this post is based on:
Pro on SiteLogic. Logi: up to 60 messages a day. Logi also stops at US$15 of model cost in a Melbourne calendar month. The Developer Comms Kit and unlimited saved projects. The Strategy Lab simulator runs without Pro. Saving a scenario needs a signed-in account. $60/month or $600/year, ex GST. First 3 months are $30/month, ex GST, on monthly Pro.