The double squeeze: construction costs and finance costs together

ABS producer price data shows building costs accelerating while the cash rate sits at 4.60%. This article runs both through one Victorian feasibility and shows which line does more of the damage.

·Written and fact-checked . Published .·5 min read

A Victorian developer pays two bills that both rose this year. Builders charge more for materials and labour. Lenders charge more for money. Most feasibility reviews test each in turn. This article runs them together and shows which one matters more.

What the producer price data shows

The ABS Producer Price Indexes for the June quarter 2026, released on 31 July, recorded the following for output prices of building construction:

  • Building construction rose 1.4% in the quarter and 4.9% over twelve months.
  • House construction rose 2.0%, which the ABS described as the largest rise since September 2022.
  • Other residential building construction rose 0.8%.
  • Non-residential building construction rose 1.0%.

Inputs rose at a similar pace in the quarter and more slowly over the year. The ABS reported that input prices to house construction rose 2.1% in the quarter and 3.8% over twelve months. House construction output prices rose 5.9% over twelve months, which the ABS described as the highest annual rise since June quarter 2023. It named other metal products (up 2.6%, driven by aluminium windows and doors, up 3.2%), electrical equipment (up 7.4%, driven by electric cable and conduit, up 11.2%) and other materials (up 2.5%, driven by plaster products, up 4.6%) as the main contributors to the input rise. It attributed the rises to higher raw material, freight and fuel costs linked to the Middle East conflict.

The figures are national. The ABS publishes state breakdowns in its data tables, so check the Victorian series before you set a contingency.

The consumer series points the same way. The ABS CPI for August 2026 showed new dwelling prices up 5.4% over twelve months, driven by project home builders raising base prices to pass through higher labour and materials costs.

The cycle has a recent comparison. The same ABS series shows the annual rise in building construction prices at 12.8% in September 2022 and 2.2% in June 2025.

What finance cost has done

The RBA's cash rate change table records four rises in 2026: to 3.85% on 4 February, 4.10% on 18 March, 4.35% on 6 May and 4.60% effective 30 September. The 29 September statement said the Board would continue to do what it considers necessary to bring inflation sustainably back to target, including increasing the cash rate target further if needed.

SiteLogic's default holding loan rate is the cash rate plus 3.5 points of lender margin. That was 7.10% before the first 2026 rise and is 8.10% now.

Worked example: both bills in one project

The following figures are illustrative. They demonstrate the method and will vary by site, council and timing.

A developer buys land with a $2,000,000 loan and builds for $4,000,000 over 12 months. The build is drawn evenly, so its average drawn balance is half the contract price.

Base case: cost is flat and the holding rate is 7.85%.

  • Average debt: $2,000,000 land plus $2,000,000 average build draw = $4,000,000.
  • Interest: $4,000,000 × 0.0785 = $314,000.

Squeeze case: build cost rises 4.9% and the holding rate is 8.10%.

  • Build cost: $4,000,000 × 1.049 = $4,196,000.
  • Average debt: $2,000,000 + ($4,196,000 ÷ 2) = $4,098,000.
  • Interest: $4,098,000 × 0.0810 = $331,938.

| Line | Base case | Squeeze case | Change | |---|---|---|---| | Build cost | $4,000,000 | $4,196,000 | +$196,000 | | Interest | $314,000 | $331,938 | +$17,938 | | Total | $4,314,000 | $4,527,938 | +$213,938 |

The cost line accounts for $196,000 of the $213,938, or about 92%. The rate rise from 7.85% to 8.10% accounts for $10,000 of the interest change. The other $7,938 is interest on the extra construction spend. The two bills interact: a higher cost is also a larger balance to pay interest on.

This sets a full year of cost change against the latest single rise. Against all four rises of 2026 the base interest would be $4,000,000 × 0.071 = $284,000. The interest change would be $47,938 ($40,000 from the rate and $7,938 from the extra spend) and the total change $243,938. The cost line is still about 80% of the total ($196,000 ÷ $243,938).

The comparison shows where to spend your attention. A 25 basis point move is visible and scheduled. A 4.9% cost move is quieter and larger.

If the contract is fixed price

A fixed-price contract moves the $196,000 to the builder. The developer's cost in this example then falls to the $10,000 rate effect, because the price is set at signing. That protection has limits. It applies to contracts already signed, not to tenders that will be priced next quarter. It also relies on the builder staying solvent through the build, which is a risk of its own. A builder that cannot absorb a 4.9% input rise may seek a variation, slow the work or fail.

Where the rate hits revenue

Finance cost also acts on your sales side. Higher rates reduce what buyers can borrow, which can lower the price you achieve. This example holds revenue flat, so it understates the squeeze. A fair feasibility tests the sales price alongside the two cost lines.

What to check

  • Contract type. A fixed-price contract moves cost risk to the builder, but only while the builder survives. Check the builder's financial standing.
  • Price validity. Confirm how long the tender price holds and what happens after.
  • Escalation clauses. If the contract has a rise and fall clause, find out which index it uses and when it applies.
  • Sensitivity grid. Run cost at +2.5% and +5.0% against the rate at +25 and +50 basis points.
  • The next release. The ABS lists the September quarter Producer Price Indexes for 30 October, and notes a full reweight of the series in that edition. Compare like with like.
  • Local context. The Vic development conditions panel tracks building costs and the cash rate against a year ago.

This is general information and not financial advice.


Published by the SiteLogic Editorial desk. Every fact traces to a primary source. See our standards and corrections register.

Fact-checked: 3 October 2026 · Review by: 3 January 2027

Sources: abs.gov.au · abs.gov.au · rba.gov.au · rba.gov.au · abs.gov.au

Our standards·

Share this article

Get new articles by email

Weekly digest of new articles. No spam. Unsubscribe any time.

Was this useful? Try the tool this post is based on:

Pro on SiteLogic. Logi: up to 60 messages a day. Logi also stops at US$15 of model cost in a Melbourne calendar month. The Developer Comms Kit and unlimited saved projects. The Strategy Lab simulator runs without Pro. Saving a scenario needs a signed-in account. $60/month or $600/year, ex GST. First 3 months are $30/month, ex GST, on monthly Pro.

See Pro pricingFree tier stays free.