The cost of planning delay in a feasibility model

Council planning decision times translate directly into holding-cost dollars, and the effect compounds through the rest of a feasibility. How to model delay explicitly rather than folding it into a single contingency line.

·Written and fact-checked . Published .·5 min read

Why delay is a modelled cost

Every month a permit takes longer than programmed is a month of holding cost absent from the original feasibility, and it is also a month in which every other assumption in the model has extra time to move: the construction cost base, the sales market, the finance terms. Planning delay is often left to a general contingency line, but it deserves its own treatment in a feasibility, because it has a direct, quantifiable cost and its effect compounds through the model rather than simply adding a flat holding charge at the end.

What council planning performance data actually reports

Know Your Council publishes local government performance reporting, including planning application processing time measures collected under the Local Government Performance Reporting Framework. This gives a developer a genuine primary-source figure for how a specific council's planning department has actually been performing, rather than relying on anecdote or on the experience of one past application. The framework reports median and other processing time statistics by council, and because performance varies significantly between councils and between years within the same council, checking the current figure for the specific council a site sits in, rather than assuming a state-wide average, is the first and most useful step in modelling delay risk.

Translating a decision time into a holding cost

Once a developer has a current processing time figure for the relevant council, translating it into a holding cost is a matter of multiplying the additional months of delay, beyond whatever period was already assumed in the base feasibility, by the site's actual monthly holding cost. That holding cost stack includes acquisition finance interest, land tax accruing on the site while it is held, rates and any lease or licence payments, and the opportunity cost of capital that could otherwise be deployed. A developer who has only modelled construction finance interest, without separately modelling the interest cost of the acquisition period itself extending, will understate the true cost of a delayed permit by a wide margin.

Land tax as part of the holding cost stack

Land tax is a real and often underweighted component of holding cost during a delay, because it accrues annually based on the land's value while it is held, independent of whether construction has started. The SRO's land tax page sets out how land tax is assessed, including the treatment of land held by trusts and the surcharge that can apply to foreign owners, both common structures for a development site. Confirm the current rate scale and any applicable surcharge on the SRO page before modelling this line, rather than carrying forward a figure from a previous project or from general market commentary, because rate scales and thresholds are reviewed and change.

Delay compounds through the model

The reason planning delay deserves separate treatment, rather than being folded into a single holding-cost percentage, is what it touches beyond the finance line. A longer permit period extends the time over which land tax accrues, extends the period acquisition finance interest is charged, pushes the construction start date into whatever cost environment exists by then, and pushes the sales campaign into whatever market conditions exist by then too. A feasibility built around a fixed permit timeline treats delay as if it only touches finance; in practice, time is the input every other line in the model is built against, so a longer permit period changes the assumptions behind all of them at once.

Modelling delay explicitly

The practical approach, one Lachlan Voss sets out as a feasibility discipline in his book, The Victorian Property Developer, is to build the base case around a realistic permit timeline drawn from the specific council's actual recent performance rather than a generic industry assumption, then run a second scenario with an explicit additional delay period, translating that delay into extra land tax, extra finance interest, and a later, potentially different, construction cost and sales price assumption. Comparing the two scenarios side by side shows a developer the extra holding cost of delay, and, more usefully, the compounding effect on the whole project's return, a picture a single delay contingency percentage never reveals.

Reporting delay risk to lenders and equity partners

A two-scenario model is also a better conversation to have with whoever is funding the site. A lender or an equity partner reviewing a single feasibility with a flat delay contingency has no way to test whether that allowance is generous or thin, because it is not tied to anything they can independently check. A base case built against the specific council's current published processing time, alongside a stated delayed scenario, gives a funder a figure they can verify against the same Know Your Council data the developer used, which is a stronger basis for a facility conversation than an unreferenced percentage. It also gives the developer a defensible answer if a funder pushes back on the permit timeline assumed: "that is the current published figure for this specific council, and here is what happens if it runs longer," rather than "that is what we normally assume."

An illustrative example

The following figures are illustrative. They demonstrate the method and will vary by site, council and timing. A site acquired with a base-case permit assumption of nine months, against a council whose current published median decision time on Know Your Council is running six months longer than that assumption, might carry an additional six months of holding cost: an extra $45,000 in acquisition finance interest, a further $12,000 in accruing land tax, and $8,000 in rates and outgoings, a combined extra cost of $65,000 before any knock-on effect on the construction cost base or the sales market at the later start date. On a project with a base-case margin of $400,000, that delay alone removes over 16% of the projected return, without a single dollar of construction cost overrun.

Practical steps before you commit

Check the current published processing time for the specific council on Know Your Council before setting the base-case permit timeline, and treat the state median as a poor substitute for the local figure. Confirm the current land tax rate scale, and any surcharge that applies to the ownership structure, on the SRO's land tax page before modelling the holding cost of an extended acquisition period. Build a second, delayed scenario alongside the base case rather than a single delay contingency line, and review both again once the application is actually lodged and the council's current queue and performance become visible.


Published by the SiteLogic Editorial desk. Every fact traces to a primary source. See our standards and corrections register.

Fact-checked: 19 July 2026 · Review by: 19 July 2027

Sources: knowyourcouncil.vic.gov.au · sro.vic.gov.au

Our standards·

Share this article

Get new articles by email

Weekly digest of new articles. No spam. Unsubscribe any time.

Was this useful? Try the tool this post is based on:

Pro on SiteLogic. Logi: up to 60 messages a day. Logi also stops at US$15 of model cost in a Melbourne calendar month. The Developer Comms Kit and unlimited saved projects. The Strategy Lab simulator runs without Pro. Saving a scenario needs a signed-in account. $60/month or $600/year, ex GST. First 3 months are $30/month, ex GST, on monthly Pro.

See Pro pricingFree tier stays free.