Merrimu PSP: what 8,000 homes, delivery staging and draft levies mean for land value
Merrimu's draft precinct plan is through exhibition but not final. The delivery sequence, parcel land budget and draft development contributions plan need to be read together before a buyer prices future residential land.
Merrimu is no longer just a broad growth-area arrow on a Bacchus Marsh strategy map. The Victorian Planning Authority has exhibited a draft precinct structure plan and development contributions plan for a precinct intended to accommodate about 8,000 homes, 1,800 jobs and 24,000 residents. That is enough detail to improve a feasibility, but not enough to treat the planning outcome or levy as settled.
The commercial question is not whether Merrimu will eventually urbanise. It is whether a particular parcel can carry the timing, infrastructure, developable-area and contribution assumptions needed to support today's land price.
What changed
Public exhibition of draft Amendment C109moor ran from 6 March to 9 April 2026. The VPA's April update says 81 submissions were received and more than 150 community members were engaged. The June status update says the VPA was still reviewing and resolving submissions, working with Melbourne Water on the drainage scheme, progressing transport, bushfire and early-works analysis, and testing possible changes to roads and schools.
That status matters more than the headline dwelling number. The draft has reached a serious statutory stage, but it remains a draft. Road alignments, school locations, drainage requirements and other land-use decisions can change the amount and timing of land that becomes saleable.
The VPA project page describes a precinct of about 907 hectares north-east of Bacchus Marsh. It identifies the proposed Bacchus Marsh Eastern Link Road, the Western Renewables Link, Long Forest Reserve, quarries, existing rural-residential development and environmental constraints around the escarpment. A land model that starts with 907 hectares and applies a generic efficiency factor misses most of the work.
What the draft levy does
The draft Merrimu Development Contributions Plan uses two different demand units. The development infrastructure levy is calculated by net developable hectare. The community infrastructure levy is calculated by dwelling.
The draft records 425.78 net developable hectares and 8,063 dwellings for its demand calculation. It also contains a property-specific land budget. If the net developable area attributed to a parcel later increases through a design or land-use change, the draft says the responsible authority may require an agreement under section 173 of the Planning and Environment Act 1987 for the additional area at the contribution rate applying at the permit stage.
This is why a single precinct-wide levy assumption is not enough. The model has to know the parcel's draft net developable area, the projects allocated through the DCP, the likely dwelling yield and whether the owner expects to deliver land or works that may be credited against contributions.
The draft also states that its infrastructure costs are expressed in 2025–26 dollars and are to be adjusted annually under the plan's indexation method. A feasibility that copies a draft charge into a long-dated settlement model without indexation understates the exposure even if the base number is correct.
How to model delivery
Separate the PSP milestone from physical delivery. Finalising and approving the planning controls does not construct drainage, roads, intersections, open space or community facilities.
Start with a parcel land budget. Use the draft PSP and DCP schedules to distinguish net developable land from roads, drainage, conservation areas, community facilities and other encumbered land. Do not assume that every non-residential hectare will be acquired or credited on the same basis. The relevant treatment depends on the final plan and the delivery agreement.
Then build a contribution schedule rather than one acquisition-day cost. The draft DCP distinguishes development infrastructure from community infrastructure and anticipates staged collection and delivery. Match assumed payments to the likely permit and subdivision sequence. If a proposed works-in-kind arrangement is important to the residual land value, record it as an unconfirmed commercial assumption until the collecting agency agrees.
Finally, carry a programme sensitivity around unresolved submissions. The June update identifies drainage, transport, bushfire and early works as active workstreams. Each can affect both the sequence of land release and the amount of capital required before a stage can settle.
The 8,000-home headline is not a parcel yield
The VPA describes the precinct as delivering a mix of about 8,000 homes. The DCP uses 8,063 dwellings for demand calculations. Neither number is a promise that a purchaser can divide across gross hectares.
Yield still depends on the final land budget, density settings, topography, access, drainage, vegetation, cultural heritage, interface treatments and the location of infrastructure. Existing developed areas within the precinct may also behave differently from broadhectare parcels.
For acquisition purposes, I would treat the public dwelling number as a precinct-scale demand assumption. The parcel yield should come from the parcel plan, not from the media headline.
What to check before exchange
Read the VPA status page on the day the investment paper is signed. Merrimu is moving through submissions, and the public record can change between heads of agreement and settlement.
Match the title boundaries against the draft property-specific land budget. Confirm which parts of the parcel are treated as net developable area and which are set aside for infrastructure or constrained land.
Test at least three cases: the exhibited layout, a lower-yield case with a slower infrastructure sequence, and a case where contribution costs are indexed beyond the base year. If the residual land value only works in the exhibited case, the offer is carrying planning risk as if it were planning certainty.
Ask separately about external and enabling works. The Moorabool Shire project page explains that the DCP funds specified essential infrastructure. It does not follow that every network, authority or early-delivery cost required by a stage is captured by the levy.
Merrimu now has enough public material for disciplined underwriting. It does not yet have a final amendment, a final parcel outcome or a fixed delivery programme. The sensible acquisition model prices the draft as evidence of direction, then discounts the unresolved steps rather than pretending they have already happened.
Published by the SiteLogic Editorial desk. Every fact traces to a primary source. See our standards and corrections register.
Fact-checked: 18 July 2026 · Review by: 18 July 2027
Sources: vpa.vic.gov.au · vpa.vic.gov.au · vpa.vic.gov.au · vpa-web.s3.ap-southeast-2.amazonaws.com · haveyoursay.moorabool.vic.gov.au
Was this useful? Try the tool this post is based on:
Pro on SiteLogic. Logi: up to 60 messages a day. Logi also stops at US$15 of model cost in a Melbourne calendar month. The Developer Comms Kit and unlimited saved projects. The Strategy Lab simulator runs without Pro. Saving a scenario needs a signed-in account. $60/month or $600/year, ex GST. First 3 months are $30/month, ex GST, on monthly Pro.