Mandatory inspection stages under the Building Act

How the Building Act 1993 and Building Regulations 2018 set the notification stages a Victorian building surveyor must sign off, and what a missed inspection costs a live construction programme.

·Written and fact-checked . Published .·6 min read

Victoria's building permit system runs on a simple discipline: work does not proceed past certain points until someone independent has looked at it. The Building Act 1993 sets up that system, and the mandatory notification stages that give it teeth sit in the Building Regulations 2018 and in the conditions printed on the permit itself. For a developer managing a multi-dwelling site, those stages are not paperwork. They are the checkpoints that decide whether a build stays on programme or stalls waiting for an inspection that was never booked.

The provision

A building permit in Victoria is issued by a relevant building surveyor, known in the industry as the RBS. That role can be filled by a municipal building surveyor employed by council or by a private building surveyor engaged directly by the owner or builder. Either way, the RBS is the statutory decision-maker under the Building Act 1993 for that permit: they assess the building work against the National Construction Code and the Victorian variations, issue the permit, and then oversee compliance through to the occupancy permit or certificate of final inspection.

Inspection is where that oversight becomes concrete. The regulations set out the points in construction where the builder, or the owner-builder, must notify the RBS before work continues, and the RBS, or an inspector acting for them, has to sight the work, or accept an alternative form of evidence the regulations allow, before the next stage can proceed. The exact list of notification stages for a given job is printed on the permit, so the first place to check is the permit document itself rather than a general summary, because conditions can vary with building class and scope.

What applies

The stages exist because certain elements of a building disappear once construction moves on. Footings and reinforcement get covered by concrete. Framing gets sheeted. Waterproofing membranes get tiled over. If a defect in one of those elements is only found later, the cost of finding out is a lot higher than the cost of an inspection would have been, because rectification means opening up finished work. The regulatory answer is to force a look before the work is covered.

Who signs off matters as much as what gets checked. The RBS carries the statutory responsibility, but on multi-dwelling and larger jobs the actual site inspection is often carried out by a building inspector engaged by, or reporting to, the RBS. The builder's obligation is to notify at the correct stage and hold the works until the inspection is completed or an alternative compliance pathway under the regulations is used. A builder who continues past a notification stage without the required sign-off has created a compliance gap that the RBS, a future purchaser's building inspection, or a dispute down the track can reopen.

The Building Act 1993 also gives the RBS enforcement tools where non-compliant work is found, ranging from a direction to rectify through to more serious orders. None of that is a fixed penalty schedule worth quoting here, because the relevant provisions and their application depend on the facts of the non-compliance. The point for a developer is structural: the inspection regime is backed by statutory power, well beyond professional courtesy.

How to model it

The commercial risk in missed or late inspections is almost always programme; compliance in the abstract rarely costs anything on its own. A stage that should have taken a single site visit to clear can instead cost days if the builder has kept working past the notification point and the RBS asks for exposed work to be opened up again, or if the booking simply was not made in time and trades are left waiting on site.

The useful modelling habit is to treat each notification stage as a programme gate with its own float, the same way a lender's progress-payment milestone or a certifier's sign-off would be treated elsewhere in the build. Build in lead time for booking inspections, particularly on a site with several dwellings inspected in sequence, and assume that a stage can fail on first attempt and need a return visit. A feasibility or a construction programme that assumes every inspection clears first time, on the date requested, is assuming away one of the more common sources of slippage on medium-density jobs.

The other habit worth carrying is separating inspection risk from underlying workmanship risk. Good inspection discipline does not fix a builder who is cutting corners, and a slow inspector does not create a defect that was not already there. Both risks sit in the programme, but they come from different places and call for different mitigation: contract administration and supervision for the first, and buffer plus a responsive certifier relationship for the second.

What to check before exchange

Before committing capital to a site or a building contract, check who holds the RBS appointment and confirm they are engaged and available for the scale of the project, beyond being nominally named on the permit. For any site bought with an existing permit, get a copy of the permit and its printed inspection stages, and ask the vendor or their builder for a record of which stages have already been passed.

Confirm the inspection and notification process the RBS actually uses, because private building surveyors vary in how quickly they turn around bookings and how they handle multi-dwelling sequencing. That practical difference belongs in the programme risk assessment alongside price and reputation.

Where a project is being delivered under an existing building permit issued some time ago, check whether any of the stage requirements or the applicable version of the Building Regulations 2018 has changed since the permit issued, and confirm the current position with the RBS rather than assuming the original permit conditions still describe every current obligation.

Interaction with other controls

Inspection stages supplement the building surveyor's broader compliance function and the separate consumer protection regime that runs through domestic building contracts and insurance. A clean run of inspections supports a smooth path to occupancy permit or certificate of final inspection, but it is only one input into settlement readiness. Treat the notification stage list on the permit as the working checklist, the Building Act 1993 and Building Regulations 2018 as the source of the rules behind it, and the RBS relationship as the practical lever that decides how well the two work together on a live site.


Published by the SiteLogic Editorial desk. Every fact traces to a primary source. See our standards and corrections register.

Fact-checked: 19 July 2026 · Review by: 19 July 2027

Sources: legislation.vic.gov.au · legislation.vic.gov.au

Our standards·

Share this article

Get new articles by email

Weekly digest of new articles. No spam. Unsubscribe any time.

Was this useful? Try the tool this post is based on:

Pro on SiteLogic. Logi: up to 60 messages a day. Logi also stops at US$15 of model cost in a Melbourne calendar month. The Developer Comms Kit and unlimited saved projects. The Strategy Lab simulator runs without Pro. Saving a scenario needs a signed-in account. $60/month or $600/year, ex GST. First 3 months are $30/month, ex GST, on monthly Pro.

See Pro pricingFree tier stays free.