Gross realisable value: building it up for a townhouse project
How to build gross realisable value from comparable evidence for a Victorian townhouse project, and the common errors that inflate it.
What applies
Gross realisable value, or GRV, is the total revenue a feasibility assumes a project will achieve once every dwelling is sold. It is the single largest number in the model and the one most exposed to optimism, because unlike a cost plan, which is anchored to a quantity surveyor's measured estimate or a builder's tender, GRV is often built from an agent's appraisal that has an obvious commercial incentive to be generous. A feasibility is only as sound as its GRV build-up, and the build-up needs to come from evidence, not from what the site needs to achieve to make the numbers work.
The correct starting point is comparable sales evidence, not aspiration. A comparable sale is a dwelling that has actually settled, in a location genuinely comparable to the subject site, of a genuinely comparable typology, condition and size, within a recent enough window that the evidence still reflects current market conditions. Comparable evidence should be checked against, rather than substituted by, published valuation and price data. The Valuer-General Victoria publishes valuation data used for rating and land tax purposes across Victorian municipalities, and while it is not a substitute for an agent's or valuer's direct comparable sales analysis, it is a useful independent cross-check on whether an appraised value sits within a defensible range for the locality. Broader movement in dwelling prices across the state is tracked in the ABS Residential Property Price Indexes, which is useful for understanding the direction of the market a presale campaign is selling into, though it measures the aggregate rather than any individual project.
How to model it
Building GRV from evidence rather than aspiration follows a defined sequence:
- Assemble comparable sales for each dwelling typology in the project, drawn from settled transactions within the trade area, not asking prices or unsettled off-the-plan contracts elsewhere.
- Adjust each comparable for genuine differences from the subject dwellings, such as internal area, aspect, car parking provision, outdoor space and finish level, and document the adjustment rather than applying an unexplained round-number uplift.
- Build a rate per square metre or a rate per dwelling from the adjusted comparables, and apply it to the subject project's actual floor areas and dwelling mix rather than to a notional average.
- Cross-check the resulting appraisal against the Valuer-General's site valuation data for the locality, to identify whether the appraisal sits within a range other evidence in the same municipality would support.
- Deduct selling costs, agent commission, marketing spend and GST at the margin scheme or standard basis as applicable, to arrive at net realisable value rather than stopping at the gross headline figure.
- Sensitivity test the GRV build-up against a softer and a firmer price scenario, consistent with the direction shown in the current ABS price index release, rather than presenting only the single point estimate to a lender or equity partner.
The errors that inflate GRV
Several recurring errors push a GRV build-up above what evidence supports. The first is using comparables that are not genuinely comparable: a larger dwelling, a different typology, a materially different location, or a sale that settled long enough ago that it no longer reflects current conditions. The second is applying an unadjusted premium for "new build" or "boutique" positioning without evidence that buyers in that specific location actually pay it. The third is averaging across a wide and heterogeneous comparable set rather than building a rate specific to each dwelling typology in the mix, which can materially misstate value where the project includes both smaller and larger product. The fourth, and the most consequential, is treating the agent's initial verbal appraisal as the GRV input without independently testing it, when that appraisal is produced by a party whose fee is a percentage of the number they are quoting.
Illustrative build-up
The following figures are illustrative. They demonstrate the method and will vary by site, council and timing. Take a project of ten townhouses, five at three bedrooms and roughly 140 square metres, and five at four bedrooms and roughly 170 square metres. Comparable settled sales in the trade area for the smaller typology, adjusted for finish and car parking, might support a rate of approximately $5,200 per square metre, giving an appraised value of roughly $728,000 each. The larger typology, on a similar adjusted rate basis, might support roughly $884,000 each. Gross realisable value on this mix would be approximately $8.06 million. After selling costs, agent commission and marketing at a combined rate of, say, 3.5 per cent, net realisable value falls to roughly $7.78 million. If the Valuer-General's site data for the municipality suggests the top end of that range is optimistic relative to recent valuations, the prudent approach is to run the feasibility at the lower end of the adjusted comparable range and treat the upper end as upside, not as the base case.
Interaction with the sales campaign
GRV is not simply a static appraisal figure. It interacts directly with the presale campaign and the financing structure built around it. A GRV built from optimistic comparables inflates the apparent presale coverage achieved for a given dollar value of contracts, which can create a false sense that a lender's coverage condition is closer to being satisfied than it actually is once the true achievable price is tested in the market. It also affects the sensitivity work described elsewhere in a stress-tested feasibility, since a GRV set too high understates how much headroom actually exists before a cost overrun or a softer market erodes the margin below an acceptable threshold.
What to check before exchange
Before relying on a GRV figure to underwrite a site acquisition:
- Request the underlying comparable sales schedule from the agent or valuer, in addition to the headline appraised figure, and check each comparable's settlement date, address and adjustment rationale.
- Cross-check the appraisal against the Valuer-General Victoria data for the municipality where it is available.
- Confirm the appraisal reflects the actual dwelling mix and floor areas in the current design, not an earlier or indicative scheme.
- Check the direction of the relevant segment of the ABS Residential Property Price Indexes to understand whether the market has moved materially since the comparable evidence was gathered.
- Obtain an independent valuation, separate from the selling agent's appraisal, before relying on GRV to size debt or equity commitments.
Record keeping and review
Keep the comparable sales schedule, the adjustment rationale and the Valuer-General cross-check as a dated record attached to the feasibility, and revisit the GRV build-up at each major decision gate as new comparable evidence settles in the market. Lachlan Voss sets out this evidence-first approach to revenue modelling in his book, The Victorian Property Developer, because GRV built from aspiration rather than evidence is the single most common reason a feasibility that looked sound at acquisition fails to deliver at settlement.
Published by the SiteLogic Editorial desk. Every fact traces to a primary source. See our standards and corrections register.
Fact-checked: 19 July 2026 · Review by: 19 July 2027
Sources: abs.gov.au · land.vic.gov.au
Was this useful? Try the tool this post is based on:
Pro on SiteLogic. Logi: up to 60 messages a day. Logi also stops at US$15 of model cost in a Melbourne calendar month. The Developer Comms Kit and unlimited saved projects. The Strategy Lab simulator runs without Pro. Saving a scenario needs a signed-in account. $60/month or $600/year, ex GST. First 3 months are $30/month, ex GST, on monthly Pro.